SB 9 in California: Two Units and Urban Lot Splits, From the Statute's Text
SB 9 sits in two sections of the California Government Code. One covers building no more than two residential units on a parcel in a single-family residential zone. The other covers splitting such a parcel in two. Each has its own list of requirements, its own exclusions and the same 60-day clock. This page sets out both lists in the statute's order, in the statute's words, as the text stood when it was read from the Legislature's data on November 12, 2026.
Quick answer
Two units. A project of no more than two residential units in a single-family residential zone is considered ministerially, without discretionary review or a hearing, if the parcel and the project meet every requirement in Gov. Code §65852.21(a).
Lot split. A parcel map that divides one such parcel into no more than two parcels of approximately equal lot area is approved ministerially only if it meets every requirement in §66411.7(a). Both new parcels are at least 1,200 square feet unless a local ordinance sets a smaller minimum (§66411.7(a)(2)), and one parcel may not be smaller than 40 percent of the original parcel's lot area (§66411.7(a)(1)).
What rules a parcel out. Work that would require demolition or alteration of rent-restricted or rent-controlled housing, or of housing occupied by a tenant in the last three years; an owner's withdrawal of the property from rent or lease under Chapter 12.75 within 15 years before the application; and the historic-resource limits each section sets (§65852.21(a)(3) to (5); §66411.7(a)(3)(D) to (F)).
Clock and occupancy. The agency approves or denies within 60 days of a completed application, or the application is deemed approved (§65852.21(h)(1); §66411.7(b)(1)(B)). A lot-split applicant signs an affidavit of intent to occupy one unit as a principal residence for at least three years (§66411.7(g)(1)).
Check a lot against SB 9's conditions
Enter the lot size and answer the questions the two sections ask. For each path the checker lists every condition the section states and whether your answers meet it, with the statute's words. Where a section states an exception that depends on the site or on the city, it says so rather than answering. The full requirements are set out below.
Two units on the lot (§65852.21)
0 not met · 0 left to the city or the site · 18 not answered · 0 met
Units: no more than 2 residential units on the lot: “A proposed housing development containing no more than two residential units within a single-family residential zone shall be considered ministerially, without discretionary review or a hearing” (§65852.21(a)).
Not answered: GOV §65852.21(a); GOV §65852.21(a)(1); GOV §65913.4(a)(6)(B), 2021 version, through §65852.21(a)(2); GOV §65913.4(a)(6)(C), 2021 version, through §65852.21(a)(2); GOV §65913.4(a)(6)(D), 2021 version, through §65852.21(a)(2); GOV §65913.4(a)(6)(E), 2021 version, through §65852.21(a)(2); GOV §65913.4(a)(6)(F), 2021 version, through §65852.21(a)(2); GOV §65913.4(a)(6)(G), 2021 version, through §65852.21(a)(2); GOV §65913.4(a)(6)(H), 2021 version, through §65852.21(a)(2); GOV §65913.4(a)(6)(I), 2021 version, through §65852.21(a)(2); GOV §65913.4(a)(6)(J), 2021 version, through §65852.21(a)(2); GOV §65913.4(a)(6)(K), 2021 version, through §65852.21(a)(2); GOV §65852.21(a)(3)(A); GOV §65852.21(a)(3)(B); GOV §65852.21(a)(3)(C); GOV §65852.21(a)(4); GOV §65852.21(a)(5)(B); GOV §65852.21(a)(5)(A).
Urban lot split (§66411.7)
0 not met · 0 left to the city or the site · 22 not answered · 0 met
Units: the city is not required to permit more than 2 units on each new parcel: “a local agency shall not be required to permit more than two units on a parcel created through the exercise of the authority contained within this section” (§66411.7(j)(1)). Its standards may not preclude two units on either parcel or units under 800 square feet (§66411.7(c)(2)).
Not answered: lot size, GOV §66411.7(a)(1) and (2); GOV §66411.7(a)(3)(A); GOV §66411.7(a)(3)(B); GOV §65913.4(a)(6)(B), 2021 version, through §66411.7(a)(3)(C); GOV §65913.4(a)(6)(C), 2021 version, through §66411.7(a)(3)(C); GOV §65913.4(a)(6)(D), 2021 version, through §66411.7(a)(3)(C); GOV §65913.4(a)(6)(E), 2021 version, through §66411.7(a)(3)(C); GOV §65913.4(a)(6)(F), 2021 version, through §66411.7(a)(3)(C); GOV §65913.4(a)(6)(G), 2021 version, through §66411.7(a)(3)(C); GOV §65913.4(a)(6)(H), 2021 version, through §66411.7(a)(3)(C); GOV §65913.4(a)(6)(I), 2021 version, through §66411.7(a)(3)(C); GOV §65913.4(a)(6)(J), 2021 version, through §66411.7(a)(3)(C); GOV §65913.4(a)(6)(K), 2021 version, through §66411.7(a)(3)(C); GOV §66411.7(a)(3)(D)(i); GOV §66411.7(a)(3)(D)(ii); GOV §66411.7(a)(3)(D)(iv); GOV §66411.7(a)(3)(D)(iii); GOV §66411.7(a)(3)(E); GOV §66411.7(a)(3)(F); GOV §66411.7(a)(3)(G); GOV §66411.7(a)(3)(H); GOV §66411.7(g)(1) and (2).
The checker tests only the conditions the two sections state, against your answers; it does not say a parcel qualifies. It cannot know the city's own objective standards, the zone on the city's map, or whether the parcel is on the maps and plans the site conditions name. Statute text as read November 12, 2026.
What SB 9 does, and where it is in the Government Code
Two sections hold the law. Section 65852.21 is about what may be built on one parcel:
A proposed housing development containing no more than two residential units within a single-family residential zone shall be considered ministerially, without discretionary review or a hearing, if the proposed housing development meets all of the following requirements:— GOV §65852.21(a)
Section 66411.7 is about dividing the parcel. It names the division an urban lot split:
Notwithstanding any other provision of this division and any local law, a local agency shall ministerially approve, as set forth in this section, a parcel map for an urban lot split only if the local agency determines that the parcel map for the urban lot split meets all the following requirements:— GOV §66411.7(a)
Three points about the wording apply to everything below.
- Who is bound. In both sections a local agency is
a city, county, or city and county, whether general law or chartered
(§65852.21(i)(3); §66411.7(l)(2)). - Two units, not a duplex. The text never uses the word duplex. It speaks of two residential units, and it counts them this way:
A housing development contains two residential units if the development proposes no more than two new units or if it proposes to add one new unit to one existing unit.
(§65852.21(i)(1)). Attached buildings are addressed in one subdivision of each section: an applicationshall not be rejected solely because it proposes adjacent or connected structures provided that the structures meet building code safety standards and are sufficient to allow separate conveyance
(§65852.21(g); the same words are in §66411.7(k)). - Which text this is. Both sections are quoted as last amended by SB 1426 (Stats. 2026, Ch. 56), in effect since June 30, 2026. A later 2026 bill, AB 2601, amends both on January 1, 2027, and its text is not what is quoted here; see what changes next.
§65852.21: Amended by Stats. 2026, Ch. 56, Sec. 7. (SB 1426) Effective June 30, 2026.
§66411.7: Amended by Stats. 2026, Ch. 56, Sec. 9. (SB 1426) Effective June 30, 2026.
SB 9 requirements: what a parcel and project must meet
The two paths are separate. A two-unit project is tested against §65852.21(a). A lot split is tested against §66411.7(a). Each list below follows the statute's order; each row gives a plain statement, the statute's words and the subdivision.
Path 1: two units on one lot, the SB 9 duplex path (Gov. Code §65852.21)
The project contains no more than two residential units and is in a single-family residential zone.
“A proposed housing development containing no more than two residential units within a single-family residential zone”
GOV §65852.21(a)
Two residential units means no more than two new units, or one new unit added to one existing unit.
“A housing development contains two residential units if the development proposes no more than two new units or if it proposes to add one new unit to one existing unit.”
GOV §65852.21(i)(1)
Location: the parcel is in a city whose boundaries include some portion of a Census Bureau urbanized area or urban cluster. In an unincorporated area, it is a legal parcel wholly within one.
“The parcel subject to the proposed housing development is located within a city, the boundaries of which include some portion of either an urbanized area or urban cluster, as designated by the United States Census Bureau, or, for unincorporated areas, a legal parcel wholly within the boundaries of an urbanized area or urban cluster, as designated by the United States Census Bureau.”
GOV §65852.21(a)(1)
Site requirements borrowed from another section: the parcel satisfies Section 65913.4(a)(6)(B) to (K), in the version of that section dated September 16, 2021. Those requirements are set out there, not in this section.
“The parcel satisfies the requirements specified in subparagraphs (B) to (K), inclusive, of paragraph (6) of subdivision (a) of Section 65913.4, as that section read on September 16, 2021.”
GOV §65852.21(a)(2)
The project would not require demolition or alteration of housing whose rents are restricted to affordable levels by a recorded covenant, ordinance or law.
“the proposed housing development would not require demolition or alteration of any of the following types of housing: (A) Housing that is subject to a recorded covenant, ordinance, or law that restricts rents to levels affordable to persons and families of moderate, low, or very low income.”
GOV §65852.21(a)(3)(A)
The project would not require demolition or alteration of housing under rent or price control.
“Housing that is subject to any form of rent or price control through a public entity's valid exercise of its police power.”
GOV §65852.21(a)(3)(B)
The project would not require demolition or alteration of housing a tenant has occupied in the last three years.
“Housing that has been occupied by a tenant in the last three years.”
GOV §65852.21(a)(3)(C)
The parcel is not one on which an owner used Chapter 12.75 (commencing with Section 7060) to withdraw accommodations from rent or lease within 15 years before the application is submitted.
“The parcel subject to the proposed housing development is not a parcel on which an owner of residential real property has exercised the owner's rights under Chapter 12.75 (commencing with Section 7060) of Division 7 of Title 1 to withdraw accommodations from rent or lease within 15 years before the date that the development proponent submits an application.”
GOV §65852.21(a)(4)
The development is not located in a contributing structure within a historic district on the State Historic Resources Inventory, or historic property or district under a city or county ordinance (the wording is the statute's).
“A contributing structure within a historic district included on the State Historic Resources Inventory, as defined in Section 5020.1 of the Public Resources Code, or historic property or district pursuant to a city or county ordinance.”
GOV §65852.21(a)(5)(A)
The development is not located on a parcel individually listed as a historical resource on the State Historic Resources Inventory, or within a property individually designated or listed as a city or county landmark.
“A parcel individually listed as a historical resource included in the State Historic Resources Inventory, as defined in Section 5020.1 of the Public Resources Code, or within a property individually designated or listed as a city or county landmark under a city or county ordinance.”
GOV §65852.21(a)(5)(B)
Section 65852.21 sets no minimum lot size of its own and, in the text read for this page, contains no owner-occupancy affidavit. Both of those belong to the lot split section below. What the local agency may add through its own objective standards is under what the city can require.
Path 2: the SB 9 lot split, or urban lot split (Gov. Code §66411.7)
The application is a parcel map for an urban lot split, and the local agency determines that it meets every requirement in subdivision (a).
“a local agency shall ministerially approve, as set forth in this section, a parcel map for an urban lot split only if the local agency determines that the parcel map for the urban lot split meets all the following requirements”
GOV §66411.7(a)
Number and proportion: the map divides one existing parcel into no more than two new parcels of approximately equal lot area, and one parcel may not be smaller than 40 percent of the original parcel's lot area.
“The parcel map subdivides an existing parcel to create no more than two new parcels of approximately equal lot area provided that one parcel shall not be smaller than 40 percent of the lot area of the original parcel proposed for subdivision.”
GOV §66411.7(a)(1)
Minimum size: both new parcels are at least 1,200 square feet, unless the local agency has adopted a smaller minimum lot size by ordinance.
“(A) Except as provided in subparagraph (B), both newly created parcels are no smaller than 1,200 square feet. (B) A local agency may by ordinance adopt a smaller minimum lot size subject to ministerial approval under this subdivision.”
GOV §66411.7(a)(2)
The parcel being divided is in a single-family residential zone.
“The parcel is located within a single-family residential zone.”
GOV §66411.7(a)(3)(A)
Location: the parcel is in a city whose boundaries include some portion of a Census Bureau urbanized area or urban cluster. In an unincorporated area, it is a legal parcel wholly within one.
“The parcel subject to the proposed urban lot split is located within a city, the boundaries of which include some portion of either an urbanized area or urban cluster, as designated by the United States Census Bureau, or, for unincorporated areas, a legal parcel wholly within the boundaries of an urbanized area or urban cluster, as designated by the United States Census Bureau.”
GOV §66411.7(a)(3)(B)
Site requirements borrowed from another section: the parcel satisfies Section 65913.4(a)(6)(B) to (K), in the version of that section dated September 16, 2021. Those requirements are set out there, not in this section.
“The parcel satisfies the requirements specified in subparagraphs (B) to (K), inclusive, of paragraph (6) of subdivision (a) of Section 65913.4, as that section read on September 16, 2021.”
GOV §66411.7(a)(3)(C)
The split would not require demolition or alteration of housing whose rents are restricted to affordable levels by a recorded covenant, ordinance or law.
“The proposed urban lot split would not require demolition or alteration of any of the following types of housing: (i) Housing that is subject to a recorded covenant, ordinance, or law that restricts rents to levels affordable to persons and families of moderate, low, or very low income.”
GOV §66411.7(a)(3)(D)(i)
The split would not require demolition or alteration of housing under rent or price control.
“Housing that is subject to any form of rent or price control through a public entity's valid exercise of its police power.”
GOV §66411.7(a)(3)(D)(ii)
The same list names a parcel on which an owner used Chapter 12.75 (commencing with Section 7060) to withdraw accommodations from rent or lease within 15 years before the application is submitted.
“A parcel or parcels on which an owner of residential real property has exercised the owner's rights under Chapter 12.75 (commencing with Section 7060) of Division 7 of Title 1 to withdraw accommodations from rent or lease within 15 years before the date that the development proponent submits an application.”
GOV §66411.7(a)(3)(D)(iii)
The split would not require demolition or alteration of housing a tenant has occupied in the last three years.
“Housing that has been occupied by a tenant in the last three years.”
GOV §66411.7(a)(3)(D)(iv)
The parcel is not within a historical landmark property on the State Historic Resources Inventory, or within a site designated or listed as a city or county landmark.
“The parcel is not located within a historical landmark property included on the State Historic Resources Inventory, as defined in Section 5020.1 of the Public Resources Code, or within a site that is designated or listed as a city or county landmark pursuant to a city or county ordinance.”
GOV §66411.7(a)(3)(E)
The split does not require demolition or alteration of a contributing structure in a historic district that is on the California Register of Historical Resources or is listed or designated under a city or county ordinance.
“A contributing structure located within either a historic district that is included on the California Register of Historical Resources or within a historic district listed or designated pursuant to a city or county ordinance.”
GOV §66411.7(a)(3)(F)(i)
The split does not require demolition or alteration of an existing exterior structural wall of a structure in such a historic district.
“An existing exterior structural wall of a structure located within either a historic district that is included on the California Register of Historical Resources or within a historic district listed or designated pursuant to a city or county ordinance.”
GOV §66411.7(a)(3)(F)(ii)
No second split: the parcel was not itself created by an earlier urban lot split.
“The parcel has not been established through prior exercise of an urban lot split as provided for in this section.”
GOV §66411.7(a)(3)(G)
No adjacent splits by the same people: neither the owner nor any person acting in concert with the owner has already used an urban lot split on an adjacent parcel.
“Neither the owner of the parcel being subdivided nor any person acting in concert with the owner has previously subdivided an adjacent parcel using an urban lot split as provided for in this section.”
GOV §66411.7(a)(3)(H)
The split conforms to all applicable objective requirements of the Subdivision Map Act, except where this section expressly provides otherwise.
“A local agency shall approve an urban lot split only if it conforms to all applicable objective requirements of the Subdivision Map Act (Division 2 (commencing with Section 66410)), except as otherwise expressly provided in this section.”
GOV §66411.7(b)(2)
Do you have to live there? The affidavit (lot split only)
The lot split section requires a signed statement of intent from the applicant. It is the only owner-occupancy rule in either section:
A local agency shall require an applicant for an urban lot split to sign an affidavit stating that the applicant intends to occupy one of the housing units as their principal residence for a minimum of three years from the date of the approval of the urban lot split.— GOV §66411.7(g)(1)
- Who is exempt. The affidavit rule does not apply to an applicant that is a community land trust, as defined in Revenue and Taxation Code §402.1(a)(11)(C)(ii), or a qualified nonprofit corporation as described in Revenue and Taxation Code §214.15 (§66411.7(g)(2)). Those definitions are in the sections cited, not in this one.
- No added occupancy rules.
A local agency shall not impose additional owner occupancy standards, other than provided for in this subdivision, on an urban lot split pursuant to this section.
(§66411.7(g)(3)) - What the text does not say. The subdivision describes what the affidavit states. As read, it does not set out a penalty, a recording requirement or a way to enforce the statement.
Using both: a lot split and two units on each parcel
The two sections refer to each other in three places. That is all the text says about using them together.
- Two units on each new parcel must stay physically possible. On a lot split the agency may not apply standards
that would have the effect of physically precluding the construction of two units on either of the resulting parcels or that would result in a unit size of less than 800 square feet
(§66411.7(c)(2)). - The cap is two units per created parcel.
a local agency shall not be required to permit more than two units on a parcel created through the exercise of the authority contained within this section
(§66411.7(j)(1)). That holds notwithstanding §65852.21, §65915 and Articles 2 and 3 of Chapter 13 (commencing with Sections 66314 and 66333), which the paragraph names. For this count,“unit” means any dwelling unit, including, but not limited to, a unit or units created pursuant to Section 65852.21, a primary dwelling, an accessory dwelling unit as defined in subdivision (a) of Section 66313, or a junior accessory dwelling unit as defined in subdivision (d) of Section 66313
(§66411.7(j)(2)). - Accessory units when both sections are used.
a local agency shall not be required to permit an accessory dwelling unit or a junior accessory dwelling unit on parcels that use both the authority contained within this section and the authority contained in Section 66411.7
(§65852.21(f)).
The text states the cap parcel by parcel and does not state a combined total for the two parcels. Its words are shall not be required to permit
: they say what the agency is not required to allow, and do not by themselves forbid an agency from allowing more. A parcel created by an urban lot split cannot be split again under this section (§66411.7(a)(3)(G)).
What disqualifies a parcel or project
Each row is a way to fail one of the requirements above, with the subdivision in each section. Where a row says a section has no such condition, that is a statement about this text only.
| What rules it out | Two units (§65852.21) | Urban lot split (§66411.7) |
|---|---|---|
| The parcel is not in a single-family residential zone | §65852.21(a) | §66411.7(a)(3)(A) |
| The parcel is in a city with no portion of a Census Bureau urbanized area or urban cluster, or is an unincorporated parcel that is not a legal parcel wholly within one | §65852.21(a)(1) | §66411.7(a)(3)(B) |
| The parcel does not satisfy Section 65913.4(a)(6)(B) to (K) as that section read on September 16, 2021 (requirements set out in that section) | §65852.21(a)(2) | §66411.7(a)(3)(C) |
| The work would require demolition or alteration of housing under a recorded covenant, ordinance or law that restricts rents to levels affordable to moderate, low or very low income households | §65852.21(a)(3)(A) | §66411.7(a)(3)(D)(i) |
| The work would require demolition or alteration of housing under any form of rent or price control | §65852.21(a)(3)(B) | §66411.7(a)(3)(D)(ii) |
| The work would require demolition or alteration of housing occupied by a tenant in the last three years | §65852.21(a)(3)(C) | §66411.7(a)(3)(D)(iv) |
| An owner withdrew accommodations from rent or lease under Chapter 12.75 (commencing with Section 7060) within 15 years before the application | §65852.21(a)(4): the parcel itself is excluded | §66411.7(a)(3)(D)(iii): listed among what the split may not require demolition or alteration of |
| Historic resources (each section words these differently; see the quotations below) | §65852.21(a)(5)(A), (B) | §66411.7(a)(3)(E), (F) |
| The parcel was itself established by an earlier urban lot split | No such condition in this section | §66411.7(a)(3)(G) |
| The owner, or a person acting in concert with the owner, has already used an urban lot split on an adjacent parcel | No such condition in this section | §66411.7(a)(3)(H) |
| The map would create more than two new parcels, a new parcel under 1,200 square feet (unless a local ordinance sets a smaller minimum), or parcels that do not meet the approximately-equal and 40 percent rule | Does not apply (no map) | §66411.7(a)(1), (a)(2) |
| The project has more than two residential units | §65852.21(a), (i)(1) | The agency need not permit more than two units on a created parcel: §66411.7(j)(1) |
| The building official makes the written public health and safety finding | §65852.21(d) | §66411.7(d) |
The site requirements this page cannot list
Both sections require the parcel to satisfy subparagraphs (B) to (K), inclusive, of paragraph (6) of subdivision (a) of Section 65913.4, as that section read on September 16, 2021
(§65852.21(a)(2); §66411.7(a)(3)(C)). The reference is to a dated version of another section, not to its current text. In the version that took effect on September 16, 2021 (Stats. 2021, Ch. 160), paragraph (6) says the development is not located on a site that is any of the following, and these are the ten subparagraphs SB 9 borrows:
Not prime farmland or farmland of statewide importance, or land zoned or designated for agricultural protection by a local ballot measure.
“Either prime farmland or farmland of statewide importance, as defined pursuant to United States Department of Agriculture land inventory and monitoring criteria, as modified for California, and designated on the maps prepared by the Farmland Mapping and Monitoring Program of the Department of Conservation, or land zoned or designated for agricultural protection or preservation by a local ballot measure that was approved by the voters of that jurisdiction.”
GOV §65913.4(a)(6)(B), 2021 version
Not wetlands.
“Wetlands, as defined in the United States Fish and Wildlife Service Manual, Part 660 FW 2 (June 21, 1993).”
(a)(6)(C), 2021 version
Not within a very high fire hazard severity zone, with two exceptions the subparagraph states.
“Within a very high fire hazard severity zone, as determined by the Department of Forestry and Fire Protection pursuant to Section 51178, or within a high or very high fire hazard severity zone as indicated on maps adopted by the Department of Forestry and Fire Protection pursuant to Section 4202 of the Public Resources Code. This subparagraph does not apply to sites excluded from the specified hazard zones by a local agency, pursuant to subdivision (b) of Section 51179, or sites that have adopted fire hazard mitigation measures pursuant to existing building standards or state fire mitigation measures applicable to the development.”
(a)(6)(D), 2021 version
Not a listed or designated hazardous waste site, unless cleared for residential use.
“A hazardous waste site that is listed pursuant to Section 65962.5 or a hazardous waste site designated by the Department of Toxic Substances Control pursuant to Section 25356 of the Health and Safety Code, unless the State Department of Public Health, State Water Resources Control Board, or Department of Toxic Substances Control has cleared the site for residential use or residential mixed uses.”
(a)(6)(E), 2021 version
Not within a delineated earthquake fault zone, unless the development complies with the seismic building standards the subparagraph names.
“Within a delineated earthquake fault zone as determined by the State Geologist in any official maps published by the State Geologist, unless the development complies with applicable seismic protection building code standards”
(a)(6)(F), 2021 version
Not within a special flood hazard area (the 100-year flood), unless one of the two federal conditions the subparagraph lists is met.
“Within a special flood hazard area subject to inundation by the 1 percent annual chance flood (100-year flood) as determined by the Federal Emergency Management Agency in any official maps published by the Federal Emergency Management Agency.”
(a)(6)(G), 2021 version
Not within a regulatory floodway, unless the development has a no-rise certification.
“Within a regulatory floodway as determined by the Federal Emergency Management Agency in any official maps published by the Federal Emergency Management Agency, unless the development has received a no-rise certification in accordance with Section 60.3(d)(3) of Title 44 of the Code of Federal Regulations.”
(a)(6)(H), 2021 version
Not land identified for conservation in an adopted conservation or natural resource protection plan.
“Lands identified for conservation in an adopted natural community conservation plan”
(a)(6)(I), 2021 version
Not habitat for protected species.
“Habitat for protected species identified as candidate, sensitive, or species of special status by state or federal agencies, fully protected species, or species protected by the federal Endangered Species Act of 1973”
(a)(6)(J), 2021 version
Not land under a conservation easement.
“Lands under conservation easement.”
(a)(6)(K), 2021 version
Subparagraph (A) of that paragraph, the coastal zone, is not among the ones SB 9 borrows; each section deals with the Coastal Act in its own subdivision. The current text of §65913.4 is on the streamlined approval page and is not the version these sections point to. Whether a parcel is in one of these areas is a question of the maps and plans each subparagraph names.
Historic property: the two sections use different words
For two units, the development may not be located in A contributing structure within a historic district included on the State Historic Resources Inventory, as defined in Section 5020.1 of the Public Resources Code, or historic property or district pursuant to a city or county ordinance.
(§65852.21(a)(5)(A)), or on a parcel individually listed as a historical resource on that inventory or within a property individually designated or listed as a city or county landmark (§65852.21(a)(5)(B)).
For a lot split, the parcel may not be located within a historical landmark property included on the State Historic Resources Inventory
or within a site designated or listed as a city or county landmark (§66411.7(a)(3)(E)). Inside a historic district, the test is about the work: the split may not require demolition or alteration of a contributing structure or of An existing exterior structural wall of a structure
located in a district on the California Register of Historical Resources or one listed or designated under a city or county ordinance (§66411.7(a)(3)(F)). The State Historic Resources Inventory is defined in Public Resources Code §5020.1, which the text cites.
The withdrawal-from-rental rule
Both sections look back 15 years from the application date for an owner's use of Chapter 12.75 (commencing with Section 7060) of Division 7 of Title 1 of the Government Code to withdraw accommodations from rent or lease. In §65852.21(a)(4) the parcel itself is excluded. In §66411.7(a)(3)(D)(iii) the same parcel appears in the list of housing the split may not require demolition or alteration of. This page reports the placement as written and does not interpret the difference.
What the city or county can require, and what it cannot
Both sections let the local agency apply its own rules if they are objective. The definition is the same in each:
standards that involve no personal or subjective judgment by a public official and are uniformly verifiable by reference to an external and uniform benchmark or criterion available and knowable by both the development applicant or proponent and the public official prior to submittal— GOV §65852.21(i)(2)
The same definition is in §66411.7(l)(1). Both add that such standards may be embodied in alternative objective land use specifications and may include housing overlay zones, specific plans, inclusionary zoning ordinances and density bonus ordinances.
The city may
- Apply objective standards that do not conflict with the section. For two units: objective zoning, subdivision and design review standards (§65852.21(b)(1)). For a lot split: such standards
that are related to the design or to improvements of a parcel
and apply to a parcel created by the split (§66411.7(c)(1)). - Require a setback of up to four feet. Except for an existing structure or a same-location, same-dimensions replacement,
a local agency may require a setback of up to four feet from the side and rear lot lines
(§65852.21(b)(2)(B)(ii); §66411.7(c)(3)(B)). The paragraph names the side and rear lot lines only. - Require parking of up to one space per unit, outside the two cases listed below (§65852.21(c)(1); §66411.7(e)(3)).
- Require a percolation test for units on an onsite wastewater treatment system (two-unit section only):
a percolation test completed within the last 5 years, or, if the percolation test has been recertified, within the last 10 years
(§65852.21(c)(2)). - Require easements and street access on a lot split.
Easements required for the provision of public services and facilities.
(§66411.7(e)(1)) andA requirement that the parcels have access to, provide access to, or adjoin the public right-of-way.
(§66411.7(e)(2)) - Adopt historic district standards. For two-unit projects, objective standards
for the purposes of maintaining the historical value of a historic district listed in the California Register of Historical Resources
(§65852.21(b)(4)). - Set a smaller minimum lot size than 1,200 square feet by ordinance (§66411.7(a)(2)(B)), and, for two-unit projects, adopt or impose objective standards more permissive than those of the underlying zone (§65852.21(b)(3)).
- Adopt an implementing ordinance. Such an ordinance
shall not be considered a project under Division 13 (commencing with Section 21000) of the Public Resources Code
(§65852.21(j); §66411.7(m)). - Decline accessory units and a third unit in the cases under using both (§65852.21(f); §66411.7(j)(1)).
The city must
- Bar rentals of 30 days or less. The agency
shall require that a rental of any unit created pursuant to this section be for a term longer than 30 days
(§65852.21(e); §66411.7(h)). - Limit split lots to residential uses.
A local agency shall require that the uses allowed on a lot created by this section be limited to residential uses.
(§66411.7(f)) - Take the owner-occupancy affidavit on a lot split (§66411.7(g)(1)); see the affidavit.
The city may not
- Use standards that make two units, or 800 square feet each, physically impossible. For two units, no standard
that would have the effect of physically precluding the construction of up to two units or that would physically preclude either of the two units from being at least 800 square feet in floor area
(§65852.21(b)(2)(A)). For a lot split, no standard that would physically preclude two units on either resulting parcel or result in a unit size of less than 800 square feet (§66411.7(c)(2)). - Require a setback for an existing structure or its same-footprint replacement.
no setback shall be required for an existing structure or a structure constructed in the same location and to the same dimensions as an existing structure
(§65852.21(b)(2)(B)(i); §66411.7(c)(3)(A)). - Apply standards that single these projects out. For two units, the agency may not impose objective standards
that do not apply uniformly to development within the underlying zone
(§65852.21(b)(3)). - Require parking in two cases. Where
The parcel is located within one-half mile walking distance of either a high-quality transit corridor, as defined in subdivision (b) of Section 21155 of the Public Resources Code, or a major transit stop, as defined in Section 21064.3 of the Public Resources Code.
(§65852.21(c)(1)(A); §66411.7(e)(3)(A)), and whereThere is a car share vehicle located within one block of the parcel.
(§65852.21(c)(1)(B); §66411.7(e)(3)(B)). The two transit terms are defined in Public Resources Code §21155 and §21064.3, not in these sections. - Reject a project only because the buildings are attached. An application
shall not be rejected solely because it proposes adjacent or connected structures provided that the structures meet building code safety standards and are sufficient to allow separate conveyance
(§66411.7(k); §65852.21(g)). - Demand street dedications or offsite work for a lot split. The agency
shall not impose regulations that require dedications of rights-of-way or the construction of offsite improvements for the parcels being created as a condition of issuing a parcel map for an urban lot split
(§66411.7(b)(3)). - Make a lot split wait on fixing old zoning nonconformities. The agency may not require
the correction of nonconforming zoning conditions
as a condition of ministerial approval of the parcel map (§66411.7(i)). - Add owner-occupancy rules to a lot split beyond the affidavit (§66411.7(g)(3)).
- Hold a discretionary review. A qualifying two-unit project is considered
ministerially, without discretionary review or a hearing
(§65852.21(a)); a lot split application is approved or deniedministerially without discretionary review
(§66411.7(b)(1)(A)).
The denial standard
A project that meets subdivision (a) can still be denied, on one written finding. The two-unit section reads:
Notwithstanding subdivision (a), a local agency may deny a proposed housing development project if the building official makes a written finding, based upon a preponderance of the evidence, that the proposed housing development project would have a specific, adverse impact, as defined and determined in paragraph (2) of subdivision (d) of Section 65589.5, upon public health and safety for which there is no feasible method to satisfactorily mitigate or avoid the specific, adverse impact.— GOV §65852.21(d)
Section 66411.7(d) gives the same test for denying an urban lot split, also keyed to the impact of the proposed housing development project
. The finding is the building official's, it is in writing, and it rests on a preponderance of the evidence. The term it turns on is defined in Government Code §65589.5(d)(2), which is part of the law covered on the Housing Accountability Act page; the definition is not repeated in these sections.
Process and deadlines the statute sets
- A completed application starts the clock. Both sections count from
the date the local agency receives a completed application
(§65852.21(h)(1); §66411.7(b)(1)(B)). Neither section as read says what a completed application contains or how completeness is decided. - 60 days to approve or deny. An application
shall be considered and approved or denied within 60 days from the date the local agency receives a completed application
(§65852.21(h)(1); §66411.7(b)(1)(B)). - Deemed approved after 60 days.
If the local agency has not approved or denied the completed application within 60 days, the application shall be deemed approved.
(§65852.21(h)(1); §66411.7(b)(1)(B)) - A denial comes with written reasons and a fix list, inside the same 60 days. The permitting agency must
return in writing a full set of comments to the applicant with a list of items that are defective or deficient and a description of how the application can be remedied by the applicant
(§65852.21(h)(2); §66411.7(b)(1)(C)). - No hearing for a two-unit project. It is considered
without discretionary review or a hearing
(§65852.21(a)). The lot split section says the application is decided ministerially without discretionary review (§66411.7(b)(1)(A)). - In the coastal zone, the Coastal Act still applies. Neither section supersedes or lessens the California Coastal Act of 1976,
except that the local agency shall not be required to hold public hearings for coastal development permit applications for a housing development pursuant to this section
(§65852.21(k); §66411.7(n) says the same for urban lot splits).
These two sections, as read, do not set an application fee, an appeal procedure, or a date by which an approval or a parcel map expires. Those questions are not answered on this page.
Is SB 9 still in effect? The court cases
Two groups of cities have sued over SB 9. Each case is listed below in date order with the court's own words, as its records read on November 27, 2026. This page reports the records; it does not predict what the courts will do.
City of Redondo Beach et al. v. Bonta et al.
“In 2022, a group of charter cities in California filed a petition for writ of mandate against the State of California and Rob Bonta, in his capacity as the Attorney General of California (collectively the State), seeking to halt enforcement of SB 9 on the ground that it was an unconstitutional infringement on their municipal power.”
- April 22, 2024, Los Angeles County Superior Court: Ruling on Verified First Amended Petition for Writ of Mandate. “Accordingly, the Court finds that SB 9 is neither reasonably related to ensuring access to affordable housing nor narrowly tailored to avoid unnecessary interference in local governance. SB 9 is therefore unconstitutional as violative of the "home rule" doctrine.” Filing
- June 18, 2024, Los Angeles County Superior Court: Judgment on Petition for Writ of Mandate and Complaint for Declaratory Relief. “2. Senate Bill 9 (as codified in Government Code Sections 65852.21, 66411.7, and 66452.6) is unconstitutional. 3. A peremptory Writ of Mandate is hereby ordered directing Respondents to cease implementation and enforcement of SB 9 against Petitioners.” Filing
- June 21, 2024, Los Angeles County Superior Court: Notice of Appeal (Judgment entered June 18, 2024). Filing
- April 21, 2025, Court of Appeal of California, Second Appellate District, Division Four: Order consolidating with B338990. Docket
- November 12, 2025, Court of Appeal of California, Second Appellate District, Division Four: Unpublished Opinion (Not To Be Published in the Official Reports). “In light of SB 450, we reverse the judgment ordering issuance of a writ of mandate. The matter is remanded to the trial court to reconsider the Cities’ writ petition under the statutory scheme as amended by SB 450. As we have reversed the judgment on which it was based, we also reverse the trial court’s October 10, 2024, order granting the Cities motion for attorneys’ fees under section 1021.5. The parties are to bear their own costs on appeal.” Opinion
- March 20, 2026, Court of Appeal of California, Second Appellate District, Division Four: Remittitur issued / Case complete. “Disposition: Reversed & Remanded to trial court w/directions; 11/12/2025; Final; Signed Unpublished; Case Citation: none.” Docket
- March 20, 2026, Los Angeles County Superior Court: Appeal - Remittitur - Other Reversed & Remanded. “3/20/2026 Appeal - Remittitur - Other Reversed & Remanded NOA 06/05/2024 & NOA 06/21/2024 "R" B338990 (Clerk)” Court's case search
- October 1, 2026, Los Angeles County Superior Court: Status Conference (RE REMITTITUR) Continued to 2027-01-12. “Pursuant to written stipulation, Status Conference RE REMITTITUR scheduled for 10/01/2026 ... was rescheduled to 01/12/2027 01:30 PM” When the docket was read on November 27, 2026, it showed no ruling on the remand writ petition. Court's case search
City of Rancho Palos Verdes et al. v. State of California et al.
“General law cities Rancho Palos Verdes, Lakewood, Paramount, and Simi Valley (collectively appellants) filed a verified complaint and petition for writ of mandate challenging the constitutionality of SB 9.”
- September 4, 2025, Court of Appeal of California, Second Appellate District, Division Four: Published Opinion (Certified for Publication). “The judgment is affirmed. Respondents may recover their costs of appeal.” Opinion
- December 4, 2025, Court of Appeal of California, Second Appellate District, Division Four: Remittitur issued / Case complete. “Disposition: Affirmed in full; 09/04/2025; Final; Signed Published; Case Citation: none.” When the docket was read on November 27, 2026, it showed no Supreme Court petition entry. Docket
From the courts' opinions, the judgment and the dockets, read November 27, 2026. A later ruling is added when the records are read again.
What the state housing department says
The Department of Housing and Community Development (HCD) enforces SB 9 and publishes a fact sheet on it, dated April 2026. That is before SB 1426 amended both sections on June 30, 2026; the statute quoted on this page is the later text. Where the two sections leave a point open, the fact sheet says:
Accessory dwelling units on a lot that is not split
HCD's fact sheet: “On a site that was not created with an urban lot split, the lot would be eligible for up to two primary dwellings under SB 9 and any number of ADUs as permitted under ADU Law. For example, an applicant may propose two units pursuant to SB 9, and an ADU and JADU.”
The statute: “a local agency shall not be required to permit more than two units on a parcel created through the exercise of the authority contained within this section” (§66411.7(j)(1))
When an application is complete
HCD's fact sheet: “the Permit Streamlining Act establishes that a local agency must determine whether an application for a development project is complete within 30 days from the date the local agency received the application.”
The statute: “shall be considered and approved or denied within 60 days from the date the local agency receives a completed application” (§65852.21(h)(1))
How strictly the site exclusions apply
HCD's fact sheet: “These exemption areas must not be more or less restrictive than what is provided in statute.”
The statute: “The parcel satisfies the requirements specified in subparagraphs (B) to (K), inclusive, of paragraph (6) of subdivision (a) of Section 65913.4, as that section read on September 16, 2021.” (§65852.21(a)(2))
Access to the new parcels
HCD's fact sheet: “These requirements should be designed to facilitate access without physically precluding the lot split.”
The statute: “A requirement that the parcels have access to, provide access to, or adjoin the public right-of-way.” (§66411.7(e)(2))
HCD also writes to cities and counties about their SB 9 rules. Its enforcement letters list shows 40 SB 9 letters to 28 jurisdictions from February 21, 2023 to November 18, 2026: 32 technical assistance letters, 5 ordinance findings letters, 2 notice of violations, 1 notice of potential violation. Each jurisdiction's letters are on SB 9 by city.
HCD Housing Law Fact Sheet: Duplexes and Lot Splits (SB 9), April 2026; and HCD enforcement letters; both read November 27, 2026. The fact sheet says it is not legal advice.
SB 9, small-lot subdivisions and ADUs side by side
Four state paths, compared question by question in each statute's own words: SB 9: two units on a lot (Gov. Code §65852.21); SB 9: urban lot split (Gov. Code §66411.7); Small-lot subdivision (SB 684, SB 1123) (Gov. Code §66499.41); Accessory dwelling units (Gov. Code §66314 to §66323). “The section does not say” means the section read has no sentence on that question.
Which lots or zones
- SB 9: two units on a lot
- “within a single-family residential zone” (§65852.21(a))
- SB 9: urban lot split
- “The parcel is located within a single-family residential zone.” (§66411.7(a)(3)(A))
- Small-lot subdivision (SB 684, SB 1123)
- “Zoned to allow multifamily residential dwelling use.” “Vacant and zoned for single-family residential development.” (§66499.41(a)(2)(A))
- Accessory dwelling units
- “a local agency shall ministerially approve an application for a building permit within a residential or mixed-use zone” (§66323(a))
How many units or parcels
- SB 9: two units on a lot
- “no more than two residential units” (§65852.21(a))
- SB 9: urban lot split
- “no more than two new parcels” “a local agency shall not be required to permit more than two units on a parcel created through the exercise of the authority contained within this section” (§66411.7(a)(1), (j)(1))
- Small-lot subdivision (SB 684, SB 1123)
- “The proposed subdivision will result in 10 or fewer parcels and the housing development project on the lot proposed to be subdivided will contain 10 or fewer residential units” (§66499.41(a)(1)(A))
- Accessory dwelling units
- “One accessory dwelling unit and one junior accessory dwelling unit per lot with a proposed or existing single-family dwelling” (§66323(a)(1), one of the combinations listed)
Minimum size of a new parcel
- SB 9: two units on a lot
- The section does not say.
- SB 9: urban lot split
- “both newly created parcels are no smaller than 1,200 square feet” (§66411.7(a)(2)(A))
- Small-lot subdivision (SB 684, SB 1123)
- “the newly created parcels are no smaller than 600 square feet” “If the parcels are zoned for single-family residential use, the newly created parcels are no smaller than 1,200 square feet.” (§66499.41(a)(3))
- Accessory dwelling units
- The section does not say.
Owner occupancy
- SB 9: two units on a lot
- The section does not say.
- SB 9: urban lot split
- “A local agency shall require an applicant for an urban lot split to sign an affidavit stating that the applicant intends to occupy one of the housing units as their principal residence for a minimum of three years from the date of the approval of the urban lot split.” (§66411.7(g)(1))
- Small-lot subdivision (SB 684, SB 1123)
- The section does not say.
- Accessory dwelling units
- “No additional standards, other than those provided in Section 66314, shall be used or imposed, including an owner-occupant requirement” (§66315)
The approval clock
- SB 9: two units on a lot
- “If the local agency has not approved or denied the completed application within 60 days, the application shall be deemed approved.” (§65852.21(h)(1))
- SB 9: urban lot split
- “If the local agency has not approved or denied the completed application within 60 days, the application shall be deemed approved.” (§66411.7(b)(1)(B))
- Small-lot subdivision (SB 684, SB 1123)
- “If the local agency does not approve or deny a completed application within 60 days, the application shall be deemed approved.” (§66499.41(c))
- Accessory dwelling units
- “The permitting agency shall either approve or deny the application to create or serve an accessory dwelling unit within 60 days from the date the permitting agency receives a completed application if there is an existing single-family or multifamily dwelling on the lot.” (§66317)
What the agency may deny on
- SB 9: two units on a lot
- “a local agency may deny a proposed housing development project if the building official makes a written finding, based upon a preponderance of the evidence, that the proposed housing development project would have a specific, adverse impact” (§65852.21(d))
- SB 9: urban lot split
- “a local agency may deny an urban lot split if the building official makes a written finding, based upon a preponderance of the evidence, that the proposed housing development project would have a specific, adverse impact” (§66411.7(d))
- Small-lot subdivision (SB 684, SB 1123)
- “A local agency may deny the issuance of a parcel map, a tentative map, or a final map if it makes a written finding, based upon a preponderance of the evidence, that the proposed housing development project would have a specific, adverse impact” (§66499.41(f))
- Accessory dwelling units
- The section does not say.
Short-term rental
- SB 9: two units on a lot
- “A local agency shall require that a rental of any unit created pursuant to this section be for a term longer than 30 days.” (§65852.21(e))
- SB 9: urban lot split
- “A local agency shall require that a rental of any unit created pursuant to this section be for a term longer than 30 days.” (§66411.7(h))
- Small-lot subdivision (SB 684, SB 1123)
- The section does not say.
- Accessory dwelling units
- “A local agency shall require that a rental of the accessory dwelling unit created pursuant to this section be for a term longer than 30 days.” (§66323(e))
Text as read: SB 9 sections November 12, 2026; §66499.41 November 12, 2026, in the version in force that day (the Legislature's history line makes another version operative on January 1, 2027); the accessory dwelling unit sections November 27, 2026. Each path has more conditions than these rows; each page sets them out in full.
What changed in 2026, and what changes next
SB 1426 (Stats. 2026, Ch. 56): GOV §65852.21 amended; GOV §66411.7 amended
In effect since June 30, 2026; its changes are in the text quoted on this page.
Bill title as printed: “Planning and zoning: annual report.” What SB 1426 changes, in the Legislative Counsel's words
AB 2601 (Stats. 2026, Ch. 955): GOV §65852.21 amended; GOV §66411.7 amended, added
Takes effect January 1, 2027. Its changes are not yet in the text quoted on this page.
Bill title as printed: “Planning and zoning: housing development: streamlined approval and subdivisions.” What AB 2601 changes, in the Legislative Counsel's words
In the bill's own words: SEC. 1
Bill section SECTION 1 amends GOV §65852.21; quoted subdivisions (h)(3) (bill version 20250AB260194CHP, chaptered 2026-09-30). See the SB 1116 note: SB 1090 SEC. 7(c)/8(c) fold AB 2601's amendments to §65852.28 and §66499.41 into SB 1090 Sec. 2.3/4.3.
(3) (A) An application for a proposed housing development submitted pursuant to this section shall be eligible for concurrent processing with an application for a parcel map for an urban lot split submitted pursuant to Section 66411.7. (B) (i) Notwithstanding subparagraph (A), a local agency’s issuance of building permits, grading permits, or certificates of occupancy for a proposed housing development may be conditioned upon the applicant first obtaining approval and recording a parcel map for eligible parcels pursuant to Section 66411.7.
This is the chaptered bill's text for the passages named, not the whole amended section.
In the bill's own words: SEC. 4
Bill section SEC. 4 amends GOV §66411.7; quoted subdivisions (b)(4) (bill version 20250AB260194CHP, chaptered 2026-09-30). See the SB 1116 note: SB 1090 SEC. 7(c)/8(c) fold AB 2601's amendments to §65852.28 and §66499.41 into SB 1090 Sec. 2.3/4.3.
(4) An application for a parcel map for an urban lot split shall be eligible for concurrent processing with an application for a proposed housing development submitted pursuant to Section 65852.21.
This is the chaptered bill's text for the passages named, not the whole amended section.
The text quoted on this page is SB 1426's (Stats. 2026, Ch. 56), an urgency statute effective June 30, 2026. It followed SB 450 (Stats. 2024, Ch. 286) and AB 1061 (Stats. 2025, Ch. 505), each of which amended both sections. AB 2601 (Stats. 2026, Ch. 955) amends both sections effective January 1, 2027; this page does not describe its changes.
Neither section, as read, states an operative date, a sunset or a repeal date of its own. The one fixed date in the text is the cross-reference to another section as that section read on September 16, 2021
(§65852.21(a)(2); §66411.7(a)(3)(C)). For the other housing bills chaptered this year, see California housing laws taking effect in 2027.
How much SB 9 is used: permit units reported to the state
Key findings: SB 9 in the state's reports
California cities and counties reported 1,457 housing units with building permits under SB 9 in 2025, up from 1,024 in 2024 (+42%).
Units on report rows that record SB 9, as each city and county reported them to the Department of Housing and Community Development; a count of units, not of lot splits or applications.
Data: report years 2024 and 2025. Permalink
127 of the 534 cities and counties in the reports have reported at least one SB 9 permit unit since 2022: 2,912 units in all.
Units on report rows that record SB 9, as each city and county reported them to the Department of Housing and Community Development; a count of units, not of lot splits or applications.
Data: report years 2022 to 2025. Permalink
The City of Los Angeles reports 2,013 of the 2,912 (69%); the ten largest reporters, 82%.
Units on report rows that record SB 9, as each city and county reported them to the Department of Housing and Community Development; a count of units, not of lot splits or applications.
Data: report years 2022 to 2025. Permalink
By type, the SB 9 permit units are 1,568 single-family detached, 912 in buildings of two to four units, 389 accessory dwelling units and 40 single-family attached.
Units on report rows that record SB 9, as each city and county reported them to the Department of Housing and Community Development; a count of units, not of lot splits or applications. Types are the reports' unit categories; categories with fewer than 10 units are not named.
Data: report years 2022 to 2025. Permalink
Cities and counties listed 790 SB 9 lot split applications in their 2021 to 2025 progress reports (53 of them combined with two units), beside 1,899 applications for two units without a split.
Applications each jurisdiction listed in Table A of its annual progress report under the SB 9 lot split or two-unit path, as reported; a count of applications, not of approved splits.
Data: report years 2021 to 2025. Permalink
In 2025 the reports also record 682 SB 9 units entitled and 540 completed.
Units on report rows that record SB 9, as each city and county reported them to the Department of Housing and Community Development; a count of units, not of lot splits or applications.
Data: report year 2025. Permalink
Source: California Department of Housing and Community Development, Annual Progress Report data (Table A2). Computed from our dataset “SB 9 units by jurisdiction and report year” (version 2026-11-27); download the CSV. Free to reuse under CC BY 4.0. Findings update when the data does.
California cities and counties file an annual progress report on housing with the Department of Housing and Community Development (HCD). The figures below count housing units with building permits whose report row records SB 9, as each jurisdiction reported it. Across report years 2018 to 2025, 127 jurisdictions reported at least one such unit, 2,912 units in all. The first report year with any is 2022. In 2025, the latest year HCD has published, the statewide figure is 1,457 of 161,469 permitted units of all kinds.
| Report year | SB 9 permit units | All building-permit units |
|---|---|---|
| 2018 | 0 | 117,736 |
| 2019 | 0 | 140,821 |
| 2020 | 0 | 137,181 |
| 2021 | 0 | 159,402 |
| 2022 | 16 | 176,190 |
| 2023 | 415 | 164,678 |
| 2024 | 1,024 | 157,004 |
| 2025 | 1,457 | 161,469 |
The next table lists the 25 jurisdictions reporting the most SB 9 permit units, all report years combined. Los Angeles (Los Angeles County) reports 2,013 of the 2,912.
| # | Jurisdiction | County | SB 9 permit units, all years | Of which 2025 |
|---|---|---|---|---|
| 1 | Los Angeles | Los Angeles | 2,013 | 1,012 |
| 2 | Ridgecrest | Kern | 66 | 16 |
| 3 | Garden Grove | Orange | 63 | 31 |
| 4 | Long Beach | Los Angeles | 54 | 54 |
| 5 | Los Angeles County | Los Angeles | 50 | 30 |
| 6 | Burbank | Los Angeles | 31 | 23 |
| 7 | Fresno | Fresno | 26 | 22 |
| 8 | Riverside | Riverside | 25 | 17 |
| 9 | Saratoga | Santa Clara | 24 | 0 |
| 10 | San Francisco | San Francisco | 23 | 11 |
| 11 | Mountain View | Santa Clara | 22 | 5 |
| 12 | San Diego County | San Diego | 21 | 14 |
| 13 | Campbell | Santa Clara | 20 | 14 |
| 14 | Los Gatos | Santa Clara | 20 | 16 |
| 15 | Arvin | Kern | 17 | 0 |
| 16 | El Cajon | San Diego | 17 | 5 |
| 17 | Hawthorne | Los Angeles | 16 | 13 |
| 18 | Soledad | Monterey | 16 | 0 |
| 19 | Menlo Park | San Mateo | 14 | 8 |
| 20 | Sacramento | Sacramento | 10 | 7 |
| 21 | San Jose | Santa Clara | 10 | 4 |
| 22 | Chula Vista | San Diego | 9 | 6 |
| 23 | East Palo Alto | San Mateo | 9 | 0 |
| 24 | Visalia | Tulare | 9 | 6 |
| 25 | Orinda | Contra Costa | 8 | 4 |
Every jurisdiction that reports an SB 9 figure, with entitled and completed units, the share of its homes in the zones SB 9 names and its own SB 9 page, is on SB 9 by city.
- What is counted. Units with building permits on report rows whose state-law field contains “SB 9”. It is a count of units, not of applications, parcels or lot splits.
- Self-reported. Each figure is what the jurisdiction entered in its own report. This site has not checked the figures against local permit records, and HCD revises its published data.
- No parcel data. The files hold no parcel, address or applicant, so they cannot show whether a given lot used SB 9.
Every jurisdiction's permits, housing element status and progress against its housing need are on California housing data by city.
What SB 9 does to the property tax bill
The two SB 9 sections say nothing about property tax. The Revenue and Taxation Code does, through its rules on new construction, and the Board of Equalization has written about subdivision maps in general.
A new unit is new construction
“Newly constructed” and “new construction” means: (1) Any addition to real property, whether land or improvements, including fixtures, since the last lien date;— §70(a)
Only the new part gets a new base year value; the rest keeps the one it has:
The assessor shall determine the new base year value for the portion of any taxable real property which has been newly constructed. The base year value of the remainder of the property assessed, which did not undergo new construction, shall not be changed.— §71
While it is being built: “New construction in progress on the lien date shall be appraised at its full value on that date and each lien date thereafter until the date of completion” (§71). On completion the supplemental assessment follows: “whenever a change in ownership occurs or new construction resulting from actual physical new construction on the site is completed, the assessor shall appraise the property changing ownership or the new construction at its full cash value” (§75.10(a)). The Board's list of examples of new construction includes “e. The conversion of a single-family residence to a duplex” (annotation 610.0060).
Estimate the yearly tax on the value a new unit adds
The one-time bill for the months left in the year is on the supplemental property tax calculator, and an accessory unit's effect on the bill is on how much an ADU raises property taxes.
Splitting the lot: what the Board has said about new parcels
The Board of Equalization has published nothing on SB 9 lot splits as such: a search of its site on November 27, 2026 found only a 2021 summary of the bill. Its annotations on subdivision maps in general say:
- “When a new subdivision map is filed and new lot parcels are created, there are no grounds for reappraisal.” “The base-year value placed upon the lots should be an allocated portion of the prior base-year value of the acreage involved.” “Allocation may be done in several ways, but in those instances where the lots are relatively equal in utility, a square-foot basis is preferred.”Property Tax Annotation 170.0105
- “When allocating a factored base year value due to a rearrangement of parcels but without a change in ownership or new construction, the allocation need only be reasonable in relation to the relative value of each new parcel and should be based on appraisal judgment.” “Article XIII A of the California Constitution requires only that there be no change to the overall factored base year value.”Property Tax Annotation 170.0013
These annotations do not mention SB 9. A sale of one of the new parcels, or a transfer of either, is a separate question under the change-in-ownership rules, which this section does not cover. Annotations read November 27, 2026; statute text read October 25, 2026.
What this page does not cover
- Local zoning and objective standards. Each city and county may adopt its own implementing ordinance and objective standards (§65852.21(b)(1), (j); §66411.7(c)(1), (m)). None of them is described here, including whether a given parcel is in a single-family residential zone.
- The facts of a parcel. Census designation, tenancy in the last three years, rent restrictions, historic listings and any earlier lot split are questions of fact for the site.
- Definitions held in other sections. The site requirements of §65913.4(a)(6)(B) to (K) as that section read on September 16, 2021; a specific, adverse impact (§65589.5(d)(2)); a high-quality transit corridor and a major transit stop (Public Resources Code §21155(b), §21064.3); the State Historic Resources Inventory (Public Resources Code §5020.1); Chapter 12.75 of Division 7 of Title 1; and the two Revenue and Taxation Code definitions in §66411.7(g)(2).
- The other small-lot path. A separate state law covers small-lot subdivisions; see SB 684 small-lot subdivisions.
- Accessory dwelling units. Sections 65852.21(f) and 66411.7(j) deal with accessory dwelling units only as far as quoted above. The rules for building one are a separate body of law; see California ADU laws. For what an added unit does to the tax bill, see how much an ADU raises property taxes in California.
- Other housing laws that may apply to the same site. Section 65915, named in §66411.7(j)(1), is on the density bonus law page. The full set is on the housing and land use law hub.
- The Subdivision Map Act and the Coastal Act. A lot split must conform to the Map Act's applicable objective requirements (§66411.7(b)(2)) and both sections leave the Coastal Act in force (§65852.21(k); §66411.7(n)). Neither act is set out here.
- Anything the two sections do not mention. As read, they say nothing about private deed restrictions or homeowners association rules, fees, utility connections, financing, or how a completed unit or new parcel is assessed for property tax.
Frequently Asked Questions
Can I split my lot under SB 9 in California?
Only if the parcel map meets every requirement in Government Code §66411.7(a). The map may create “no more than two new parcels of approximately equal lot area” (§66411.7(a)(1)). The parcel must be in a single-family residential zone (§66411.7(a)(3)(A)) and inside a city that includes part of a Census Bureau urbanized area or urban cluster, or, if unincorporated, be a legal parcel wholly within one (§66411.7(a)(3)(B)). It must meet the site requirements of Section 65913.4(a)(6)(B) to (K) as that section read on September 16, 2021 (§66411.7(a)(3)(C)). The split must not require demolition or alteration of the housing listed in §66411.7(a)(3)(D), the parcel must not be within the landmark property or site described in §66411.7(a)(3)(E), the split must not require the demolition or alteration in a historic district described in §66411.7(a)(3)(F), the parcel must not itself come from an earlier urban lot split (§66411.7(a)(3)(G)), and neither the owner nor anyone acting in concert with the owner may have used an urban lot split on an adjacent parcel (§66411.7(a)(3)(H)).
What is the minimum lot size for an SB 9 lot split?
Two rules apply together. Under Government Code §66411.7(a)(2)(A), “both newly created parcels are no smaller than 1,200 square feet”, except that a local agency may adopt a smaller minimum lot size by ordinance (§66411.7(a)(2)(B)). Under §66411.7(a)(1), the two parcels are of approximately equal lot area, “provided that one parcel shall not be smaller than 40 percent of the lot area of the original parcel proposed for subdivision”. The section as read sets no minimum size for the original parcel other than what those two rules produce.
Do I have to live on the property to use SB 9?
For an urban lot split, the statute requires an affidavit of intent. Government Code §66411.7(g)(1) says the local agency shall require the applicant “to sign an affidavit stating that the applicant intends to occupy one of the housing units as their principal residence for a minimum of three years from the date of the approval of the urban lot split”. That does not apply to a community land trust or a qualified nonprofit corporation as those terms are defined in the Revenue and Taxation Code sections §66411.7(g)(2) cites, and the agency may not impose any other owner occupancy standard on an urban lot split (§66411.7(g)(3)). Section 65852.21, the two-unit section, contains no owner-occupancy affidavit of its own in the text read for this page.
How many units can I build with SB 9 in California?
Government Code §65852.21(a) covers a housing development “containing no more than two residential units within a single-family residential zone”, which means no more than two new units, or one new unit added to one existing unit (§65852.21(i)(1)). After an urban lot split, a local agency “shall not be required to permit more than two units on a parcel created through the exercise of the authority contained within this section” (§66411.7(j)(1)), and a unit there means any dwelling unit, including a primary dwelling, an accessory dwelling unit and a junior accessory dwelling unit (§66411.7(j)(2)). The agency also may not apply standards that would physically preclude two units on either resulting parcel (§66411.7(c)(2)). The text sets the cap per parcel; it does not state a combined total for the two parcels.
Can a city deny an SB 9 application?
An application that does not meet the requirements of §65852.21(a) or §66411.7(a) does not qualify for ministerial treatment under those subdivisions. Where the requirements are met, each section still lets the agency deny if “the building official makes a written finding, based upon a preponderance of the evidence, that the proposed housing development project would have a specific, adverse impact” on public health and safety that cannot feasibly be mitigated or avoided (§65852.21(d); §66411.7(d)). The term specific, adverse impact is defined in Government Code §65589.5(d)(2), which the text cites and this page does not reproduce. An agency that denies must, within the 60-day period, return in writing a full set of comments listing what is defective or deficient and how the applicant can remedy it (§65852.21(h)(2); §66411.7(b)(1)(C)).
How long does a city have to approve an SB 9 application?
Sixty days from a completed application, for both paths. Government Code §65852.21(h)(1) and §66411.7(b)(1)(B) each say the application shall be considered and approved or denied “within 60 days from the date the local agency receives a completed application”, and each adds: “If the local agency has not approved or denied the completed application within 60 days, the application shall be deemed approved.” Neither section as read says what makes an application complete.
Can SB 9 units be rented for less than 30 days?
No. Both sections put the duty on the local agency: it “shall require that a rental of any unit created pursuant to this section be for a term longer than 30 days” (Government Code §65852.21(e); the same words are in §66411.7(h)). For a lot created by an urban lot split, the agency must also require that the uses allowed be limited to residential uses (§66411.7(f)).
Is SB 9 still in effect in California?
The two sections are in the Government Code as quoted on this page. Two court cases have challenged them. In the charter cities' case, the Los Angeles County Superior Court ruled on April 22, 2024: “Accordingly, the Court finds that SB 9 is neither reasonably related to ensuring access to affordable housing nor narrowly tailored to avoid unnecessary interference in local governance. SB 9 is therefore unconstitutional as violative of the "home rule" doctrine.” On November 12, 2025 the Court of Appeal reversed: “In light of SB 450, we reverse the judgment ordering issuance of a writ of mandate. The matter is remanded to the trial court to reconsider the Cities’ writ petition under the statutory scheme as amended by SB 450.” On the trial court's register as read on November 27, 2026, the next entry reads: “Pursuant to written stipulation, Status Conference RE REMITTITUR scheduled for 10/01/2026 ... was rescheduled to 01/12/2027 01:30 PM” In the general law cities' case, the trial court entered judgment for respondents. It concluded that, as general law cities, appellants could not invoke the municipal affairs doctrine, and on September 4, 2025 the Court of Appeal ruled: “The judgment is affirmed. Respondents may recover their costs of appeal.”
Learn More
Statute text on this page: Government Code §65852.21 and §66411.7, read November 12, 2026; Government Code §65913.4 as it read on September 16, 2021, read November 13, 2026. These laws are amended most years; the dates show how current each quotation is.
Sources: Government Code §65852.21 and §66411.7, current text as amended by SB 1426 (Stats. 2026, Ch. 56), from the Legislature's bulk data (build of November 8, 2026); quotations verbatim and checked against that text when the site is built. Bills chaptered in 2026 from the same bulk data. Permit figures: HCD annual progress report open data (Table A2), downloaded November 12, 2026, as reported by each jurisdiction. The section links open the Legislature's site; verify before relying. General information about California law, not legal advice.
Last reviewed: November 2026.